P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
Options:
A. 5 5 /11 B. 5 6 /11
C. 6 5 11 D. 6 6 /11
Answer: A
Explanation: